Current Road Projects

Projects Under Construction

If you have any questions or concerns regarding a project, please contact Public Works Engineering, at 972-304-3679.

Tax 2020 Denton Tap Road Intersection Improvements

A design contract for the reconstruction of four intersections along Denton Tap Road was awarded to Kimley-Horn in the Summer of 2019. Those four intersections are:  Parkway,  Southwestern,  Sandy Lake,  and  Bethel School. The project consists of:

  • Construction of turn lanes
  • Reconstruction of sidewalks and ramps
  • Traffic signal work

Bid Awarded

The project was awarded to Rebcon Inc. for a total contract amount of $2,777,148.70. Construction began in the Spring of 2021 and is anticipated to complete in the Fall of 2022.

Latest Update

Pre-construction meeting was held on 04-15-2021. The project began on 04-19-2021. This project is 95% complete. Signal and paving work is currently in progress at S Denton Tap Rd & Bethel School Rd intersection. Southwestern Blvd & S Denton Tap Rd turn lane is complete. N Denton Tap & Parkway Blvd intersection is complete and Sandy Lake Rd & N Denton Tap Rd intersection is complete. The improvement of the right turn lane on the SH 121 Service Road & N Denton Tap Rd have begun.

ST 16-01A S Belt Line Road

View the S Belt Line Reconstruction page for more information. Read through weekly project updates on the S Belt Line Reconstruction Updates page

Tax 2021A Dividend Drive, Mockingbird Lane, & Falcon Lane Panel Replacement

The design for the panel replacement project of Dividend Drive, Mockingbird Lane, and Falcon Lane was completed by the City of Coppell’s Public Works Department. The project consists of:

  • Full depth concrete panel replacement
  • Pot holes and cracked panels will be addressed

Bid Awarded

The project was awarded to Advanced Contracting for a total contract amount of $1,457,364.00. Construction to begin in the Summer of 2022 and to be completed Winter 2023.

Latest Update

Construction began on 06-01-2022. This project is 60% complete. Mockingbird and Falcon are complete, work is underway on Dividend Drive. 

Tax 2021A Royal Lane Asphalt Overlay

The complete reconstruction of Royal Lane is currently in the early stages of design. This project is an asphalt overlay that will be completed in the meantime. The project includes:  

  • An asphalt overlay on sections of Royal Lane to extend the life of the current pavement riding surface

Bid Awarded

The project is in conjunction with Dallas County for a total contract amount of $98,500. Construction to begin in the Late Summer of 2022 and will be completed in the Fall of 2022.

Latest Update

The Pre-Construction meeting was held at the end of July 2022. Milling and overlay began at the end of July 2022. This project is 61% complete. Asphalt overlay is complete except for crack sealing at a few locations. 


Projects in Design


Tax 2022A Royal Lane Reconstruction 

A design contract for the reconstruction of Royal Lane was awarded to Teague, Nall, & Perkins in the Spring of 2022 in the amount of $1,403,000. The project consists of pavement reconstruction, utility upgrades, and sidewalk improvements. Construction is anticipated to begin in 2023.

Tax 2019C Woodhurst Drive

A design contract for the reconstruction of Woodhurst Drive was awarded to Westra Consultants in the Fall of 2020 in the amount of $359,500. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Construction is anticipated to begin in 2023.

Tax 2022B Bullock Drive & Howell Drive

A design contract for the reconstruction of Bullock Drive and Howell Drive is in the preliminary stages with the engineering firm Pacheco Koch. The project consists of pavement reconstruction, utility upgrades, sidewalk installation, and drainage improvements. Construction is anticipated to begin in 2024.  

Tax 2018A Spanish Moss Drive & Jeb Court

A design contract for the reconstruction of Spanish Moss Drive and Jeb Court was awarded to Huitt Zollars, Inc. in the Summer of 2019 in the amount of $200,295. The project consists of complete pavement reconstruction, utility upgrades, and sidewalk improvements. Construction is anticipated to begin in 2024. 

Tax 2019B Southwestern Boulevard

A design contract for the reconstruction of Southwestern Blvd was awarded to Kirkman Engineering in the Fall of 2020 in the amount of $202,700. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Construction is anticipated to begin in 2025.


Future Projects



If you want to know more about Parks & Recreation projects going on in the city, please visit the City of Coppell Parks Projects page.

Sidewalk Repair Process

  1. The damaged sidewalk is demolished and removed
  2. The ground is compacted and prepared
  3. Wood forms are set and rebar is placed
  4. Concrete is poured and cures/dries typically 24 to 72 hours
  5. Control joints are saw-cut and sealant is applied to expansion joints, if any