- Home
- Government
- City Departments
- Public Works
- Current Construction Projects
- S Belt Line Reconstruction
- S Belt Line Reconstruction Updates
S Belt Line Reconstruction Updates
Friday, May 20, 2022
Utility improvements, roadway excavation, and subgrade preparation continued this week, and work on these activities will resume next week. Additionally, crews will begin pouring concrete next week!
Friday, May 13, 2022
Utility improvements, roadway excavation, and subgrade preparation continued this week, and work on these activities will resume next week.
Friday, May 6, 2022
Concrete removal along S. Belt Line continues. Crews also continue to work on subgrade preparation, utility improvements and roadway excavation.
Friday, April 29, 2022
Crews will continue concrete removal into next week. Subgrade preparation, roadway excavation and utility improvements continue.
Friday, April 22, 2022
Concrete removal will be completed next week, and crews have begun to shift to subgrade (the foundation of the pavement structure) preparation. Roadway excavation and utility improvements continue.
Friday, April 15, 2022
As concrete removal for the S. Belt Line Reconstruction project wraps up, crews are shifting their efforts to roadway excavation. Utility improvements continue.
Friday, April 8, 2022
Crews continued working on concrete removal and utility improvements. Concrete removal activities will wrap up next week, and work will shift to roadway excavation. Utility improvements will continue next week.
Friday, April 1, 2022
Crews continued working on concrete removal and utility improvements. These activities will continue in the coming week.
Friday, March 25, 2022
Crews continued working on concrete removal and utility improvements. These activities will continue in the coming week.
Friday, March 18, 2022
Crews continued working on concrete removal and utility improvements. These activities will continue in the coming week.
Friday, March 11, 2022
Construction crews completed asphalt removal. Crews will continue working on concrete removal and utility improvements in the coming week.
Friday, March 4, 2022
Construction crews reduced the roadway to one lane in each direction, plus a center lane for turning traffic. Crews began asphalt removal and utility improvements. In the coming week, crews will complete asphalt removal and will begin removing concrete.
-
Public Works
Physical Address
265 E Parkway Blvd (Engineering)
816 S Coppell Rd (Operations)
Coppell, TX 75019
Mailing Address
P.O. Box 9478
Coppell, TX 75019
-
-