S Belt Line Reconstruction Updates

Friday, February 16

Project update 02.16S Belt Line reconstruction crews are continuing to make progress on Phase 3 of reconstruction. Concrete is being poured, traffic signals are getting installed, and subgrade prep continues on the southbound lanes between Dividend Dr. and IH-635. This work will continue into next week.

Friday, February 9

Project update 02.09S Belt Line reconstruction crews continue to perform subgrade preparation, operate on traffic signals, and pour concrete on the southbound lanes between Dividend Dr. and IH-635. This work will continue next week.

Friday, February 2

Project update 02.02Like the week before, S Belt Line reconstruction crews continue to pour concrete on the southbound lanes between Dividend Dr. and IH-635. Crews are also performing subgrade preparation and traffic signal work.