S Belt Line Reconstruction Updates

  1. September 2023
  2. August 2023
  3. July 2023
  4. June 2023
  5. May 2023
  6. April 2023
  7. March 2023
  8. February 2023
  9. January 2023
  10. December 2022
  11. November 2022
  12. October 2022
  13. September 2022
  14. August 2022
  15. July 2022
  16. June 2022
  17. May 2022
  18. April 2022
  19. March 2022

Friday, September 29

Project update 9.29

S. Belt Line reconstruction crews continue to perform traffic signal work, but have started to install necessary storm drains. The quick removal of concrete and fair weather has allowed crews to work in tandem with one another as they continue reconstruction.


Friday, September 15

S. Belt Line Reconstruction Project update 09.22.2023

As with previous weeks, crews continue to remove concrete and perform traffic signal work on S. Belt Line. 


Friday, September 15

S. Belt Line Table 09.15.23

Phase three of S. Belt Line reconstruction continues with crews removing concrete and performing traffic signal work.


Friday, September 1

S. Belt Line Table 09.01.23

Phase three of S. Belt Line reconstruction is underway, beginning with the closure of the northbound lanes between Dividend Dr. and I-635. Concrete removal has already commenced, and during this phase, all traffic in this area will be rerouted to the southbound lanes. Normal traffic flow will resume at Dividend Drive.